Introduction

Transformed a vital Pathology Response Laboratory. Completed £1M project in 20 weeks, prioritising seamless hospital operations.

North Middlesex University Hospital is a district general hospital located in the London Borough of Enfield.

The hospital, which is managed by North Middlesex University Hospital NHS Trust, recently undertook a laboratory fit-out project in collaboration with our client, HSL (Health Services Laboratories).

The aim was to create a new Pathology Response Laboratory within a vacant floor area of approximately 650m2.

North Middlesex Hospital
Project Overview

North Middlesex Hospital

Location
North Middlesex Hospital
N18 1QX
Completion
Value
£1.2M
Client
HSL
Program
20 weeks
Includes
Specialist Laboratories
Sluice Rooms
Staff Rooms

Scope of Work

The project involved a comprehensive fit-out of the designated area. This included the removal of all existing partitions and bed bays and the construction of a fully functional laboratory. Key elements of the project included:

  1. Stripping the existing area of all redundant elements.
  2. Installation of lightweight partitioning to define the laboratory space.
  3. Installation of suspended ceilings.
  4. Flooring and decoration to enhance aesthetics and functionality.
  5. Incorporation of an extensive range of laboratory benches with power and data provisions.
  6. Integration of staff welfare facilities within the designated area.

Services Utilised

To successfully complete the laboratory fit-out, various services were utilised. These included:

  • HAVAC (Heating, Ventilation, and Air Conditioning)
  • Electrical
  • Plumbing
  • Data

Challenges and Solutions

A close working relationship with the hospital trust was crucial, as the adjacent areas, as well as floors above and below, were still operational during the project. Keeping noise levels to a minimum was a top priority to ensure uninterrupted hospital functions. The following strategies were implemented:

  1. Effective Communication: Continuous coordination with the hospital trust to understand their ongoing operations and scheduling work accordingly.
  2. Noise Mitigation Measures: Implementation of noise control measures such as soundproofing, scheduling noisy tasks during quieter periods, and utilizing quieter construction methods.
  3. Flexible Working Hours: Adjusting working hours to minimize disruption to the hospital’s daily activities.
  4. Collaborative Approach: Maintaining constant communication and collaboration with the hospital trust to address any concerns and find mutually agreeable solutions.

Project Outcome

Through diligent planning and close collaboration, the laboratory fit-out project at North Middlesex Hospital was successfully executed.

The project, valued at £1.2 million, was completed within the agreed schedule of 20 weeks. The newly created Pathology Response Laboratory now serves as a critical facility within the hospital, enabling efficient and effective pathology services.

The seamless integration of the laboratory within a live hospital environment demonstrates the expertise and commitment of all involved parties in delivering a successful project while prioritising patient care and hospital operations.